Court Hearing Set for Friday on Effort to Halt Oil Pipeline in Iowa

DES MOINES, Iowa (AP) — As work progresses on an oil pipeline crossing Iowa, opponents are holding protest rallies and taking the state utilities regulators to court in hopes of stopping construction.
A hearing is scheduled for Friday in Des Moines on a motion to stay construction on several parcels of land. It’s part of a lawsuit challenging the Iowa Utilities Board’s authority to give for-profit Texas oil company Dakota Access the right to condemn private farmland for the pipeline.
Company attorney Bret Dublinske says the stay is another attempt to halt the project without a legal or factual basis.
The board, meeting Tuesday, learned 60 percent of the project right-of-way is cleared, 40 percent graded and trenches are dug on about 15 percent of the needed path.
Outside the meeting two dozen opponents protested.
Related News
From Archive

- Intrepid Fiber breaks ground on fiber optic network in Superior, Colo.
- Excavator collides with I-95 overpass in Henrico, Va., causing multi-vehicle crash
- Shrewsbury, Mass., expands sewer inspections and cleaning efforts
- Two workers rescued after hours trapped in Mich. trench collapse
- Trump calls for Keystone XL pipeline revival, but developer has moved on
- Illinois overhauls Peoples Gas pipeline program, mandates focus on high-risk pipes
- Ameren Illinois to invest $140 million in natural gas pipeline replacement program
- Charlottesville, Va., to begin work on 24-inch water line for Rivanna River crossing
- Mass. governor slams Trump for ‘dangerous delay’ of $50 million in lead pipe replacement funds
Comments