Court Hearing Set for Friday on Effort to Halt Oil Pipeline in Iowa

DES MOINES, Iowa (AP) — As work progresses on an oil pipeline crossing Iowa, opponents are holding protest rallies and taking the state utilities regulators to court in hopes of stopping construction.
A hearing is scheduled for Friday in Des Moines on a motion to stay construction on several parcels of land. It’s part of a lawsuit challenging the Iowa Utilities Board’s authority to give for-profit Texas oil company Dakota Access the right to condemn private farmland for the pipeline.
Company attorney Bret Dublinske says the stay is another attempt to halt the project without a legal or factual basis.
The board, meeting Tuesday, learned 60 percent of the project right-of-way is cleared, 40 percent graded and trenches are dug on about 15 percent of the needed path.
Outside the meeting two dozen opponents protested.
Related News
From Archive

- Three Houston workers killed by hydrogen sulfide leak during sewer repair
- Trump's tariffs drive $33 million cost increase for Cincinnati sewer project
- TxDOT advances massive drainage tunnel beneath I-35 in Austin
- Funding approved for $1.3 billion, 60-mile water reuse system in southern Utah
- Is the Boring Company tunneling blind in Nashville? Experts warn rock tests fall short
Comments