After 22 Water Breaks, Lawrence Learns of Installation Woes
LAWRENCE, Kan. (AP) — Lawrence officials have learned that 13 miles of pipeline was improperly installed after 22 water main breaks.
The Lawrence Journal-World reports that the breaks have occurred over a three-week period. Director of Utilities Dave Wagner says repair and replacement costs from the breaks have totaled about $200,000, and costs could grow.
Most of the breaks occurred in piping that was only about 25 years old. The piping was projected to last for 100 years, but was installed without the wrapping or other protection needed to account for the soil conditions. He says the 13 mile span of piping is “probably not going to last that long.”
Commissioner Matthew Herbert says what happened is “a classic example of why you have to do things right the first time.”
Related News
From Archive
- OSHA investigates fatal trench collapse at Conroe construction site
- Final Lake Erie sewer tunnel project set to begin after decades-long $3 billion effort
- Texas811 launches real-time excavation detection to prevent utility strikes
- Oil pipeline struck during fiber optic construction spills into L.A. storm drains
- Fiber drilling strike triggers major sewer failure, lawsuits in Florida
- Fatal trench collapse in Mass. leads to $4.6 million OSHA penalty, dozens of violations
- Texas811 launches real-time excavation detection to prevent utility strikes
- Race Communications breaks ground on Bakersfield fiber network
- Final Lake Erie sewer tunnel project set to begin after decades-long $3 billion effort
- Inside Infrastructure: Utility locators warn of systemic failures in damage prevention process

Comments