After 22 Water Breaks, Lawrence Learns of Installation Woes
LAWRENCE, Kan. (AP) — Lawrence officials have learned that 13 miles of pipeline was improperly installed after 22 water main breaks.
The Lawrence Journal-World reports that the breaks have occurred over a three-week period. Director of Utilities Dave Wagner says repair and replacement costs from the breaks have totaled about $200,000, and costs could grow.
Most of the breaks occurred in piping that was only about 25 years old. The piping was projected to last for 100 years, but was installed without the wrapping or other protection needed to account for the soil conditions. He says the 13 mile span of piping is “probably not going to last that long.”
Commissioner Matthew Herbert says what happened is “a classic example of why you have to do things right the first time.”
Related News
From Archive
- Fatal trench collapse halts sewer construction in Massachusetts; two workers hospitalized
- Alaska LNG pipeline could require 7,000 workers at peak construction, developers say
- Ohio trench collapse kills one worker, injures two during pipe installation
- Elon Musk's Boring Co. fined for dumping drilling waste into Vegas sewer system
- $1.4 billion Midwest pipeline expansion to move more Canadian oil to U.S. Gulf
- Glenfarne Alaska LNG targets late-2026 construction start for 807-mile pipeline project
- Fatal trench collapse halts sewer construction in Massachusetts; two workers hospitalized
- Massive water line failure leaves majority of Waterbury without service
- Infrastructure failure releases 100,000 gallons of wastewater in Houston; repairs ongoing
- Pennsylvania American Water launches interactive map to identify, replace lead water service lines

Comments