City of Newburgh completes first underground tunnel, part of $32 million sewer improvement project
(UI) – The City of Newburgh successfully completed the first of three underground tunnels planned for the City’s $32 million North Interceptor Sewer Improvement Project. This phase of the project is being completed by a specially designed tunnel boring machine (TBM) capable of “micro tunneling” – an innovative, remote-operated trenchless construction method that allows for simultaneous excavation and pipe laying with minimal disruption to residents. Over a period of 35 days, the TBM broke through 487 feet of solid rock, traveling a path along Colden Street, between First Street and Second Street to complete the first tunnel.
This first section of new sewer tunnel was created by launching the TBM from inside a 50-foot-deep shaft excavated at the intersection of First Street and Colden Street, and boring the new tunnel in a northerly direction to a receiving shaft excavated at the intersection of Second Street and Colden Street. The TBM was then extracted from the Second Street shaft and commenced boring the next section of tunnel along Colden Street between Broadway and First Street on March 30th.
The North Interceptor Sewer Improvement Project is the largest and most significant infrastructure project to take place in the city in decades. The $32 million project commenced construction in April 2022 and will be completed in the Spring of 2024. At completion, the project will have installed 8,700 linear feet of new, larger-gravity sanitary sewer piping to make upgrades to the city’s combined sewer infrastructure that are crucial to protecting the water quality of the Hudson River.
Related News
From Archive
- TxDOT advances massive drainage tunnel beneath I-35 in Austin
- Glenfarne Alaska LNG targets late-2026 construction start for 807-mile pipeline project
- U.S. water reuse boom to fuel $47 billion in infrastructure spending through 2035
- $2.3 billion approved to construct 236-mile Texas-to-Gulf gas pipeline
- Major water pipe break in Puerto Rico hits over 165,000 customers
- Pennsylvania American Water launches interactive map to identify, replace lead water service lines
- Trump's tariffs drive $33 million cost increase for Cincinnati sewer project
- Utah city launches historic $70 million tunnel project using box jacking under active rail line
- Tulsa residents warned after sewer lines damaged by boring work
- Fatal trench collapse halts sewer construction in Massachusetts; two workers hospitalized

Comments