Trans Mountain completes pipe pullback for Mountain 3 HDD in Fraser Valley
(UI) — Trans Mountain successfully completed the pipe pullback for the Mountain 3 Horizontal Directional Drill (HDD) in the Fraser Valley between Hope and Chilliwack, BC.

To complete the expansion project, there are several remaining steps including obtaining outstanding approvals from the Canada Energy Regulator (CER). With the appropriate approvals and completion of remaining construction activity, Trans Mountain will commence transporting crude oil on the expanded system.
The commencement date for commercial operation of the expanded system will be May 1, 2024. Trans Mountain anticipates providing service for all contracted volumes in the month of May.
After commencement of operation of the Expansion Project, Trans Mountain will continue cleanup, reclamation, road and civil work.
Related News
From Archive

- Intrepid Fiber breaks ground on fiber optic network in Superior, Colo.
- Excavator collides with I-95 overpass in Henrico, Va., causing multi-vehicle crash
- Shrewsbury, Mass., expands sewer inspections and cleaning efforts
- Construction worker killed in trench collapse near Prosperity, S.C.
- Two workers rescued after hours trapped in Mich. trench collapse
- WES tunnel boring machine retrieved from Oregon river after seven-month project
- Illinois overhauls Peoples Gas pipeline program, mandates focus on high-risk pipes
- Ameren Illinois to invest $140 million in natural gas pipeline replacement program
- Charlottesville, Va., to begin work on 24-inch water line for Rivanna River crossing
- Mass. governor slams Trump for ‘dangerous delay’ of $50 million in lead pipe replacement funds
Comments