Trans Mountain completes pipe pullback for Mountain 3 HDD in Fraser Valley
(UI) — Trans Mountain successfully completed the pipe pullback for the Mountain 3 Horizontal Directional Drill (HDD) in the Fraser Valley between Hope and Chilliwack, BC.

To complete the expansion project, there are several remaining steps including obtaining outstanding approvals from the Canada Energy Regulator (CER). With the appropriate approvals and completion of remaining construction activity, Trans Mountain will commence transporting crude oil on the expanded system.
The commencement date for commercial operation of the expanded system will be May 1, 2024. Trans Mountain anticipates providing service for all contracted volumes in the month of May.
After commencement of operation of the Expansion Project, Trans Mountain will continue cleanup, reclamation, road and civil work.
Related News
From Archive

- HDD industry faces challenges as cities push back on fiber drilling disruptions
- 2 workers killed, 1 injured while working on sewer line in Mobile, Ala.
- Tunnel boring continues under Chesapeake Bay for $3.9 billion HRBT Expansion project
- $5.3 billion, 516-mile pipeline to connect Texas to Arizona through New Mexico
- Judge approves construction for key portion of $485 million pipeline in Larimer County, Colo.
- New products: Latest industry developments
- 31 workers rescued after LA tunnel partially collapses
- Ohio Supreme Court rules sewer line location isn’t a ‘defect’ in property dispute
- Faulconer Construction begins rock blasting for water pipeline project in Charlottesville, Va.
- $5.3 billion, 516-mile pipeline to connect Texas to Arizona through New Mexico
Comments