Austin Energy's distribution system undergoes assessment for underground feasibility
(UI) — The Austin City Council approved Austin Energy’s third-party contract for evaluating the electrical utility’s more than 12,000 miles of electrical distribution lines, the company said on Feb. 16.
Twin independent studies by engineering firm Burns & McDonnell will begin in March 2024 to assess the underground feasibility and overhead resiliency of Austin Energy’s distribution system.
The contractor will evaluate the distribution system which consists of approximately 7,000 miles of underground and 5,000 miles of overhead lines. The goal is to identify potential improvements to ensure the continued safe and reliable delivery of power to Austin Energy’s electric customers with a focus on risk management and resiliency.
“Austin Energy is excited to embark on these studies with an eye toward continually improving electric service reliability and resiliency,” said Elaine Veselka, Vice President of Electric System Engineering and Technical Services. “We feel this is much more than a ‘one size fits all’ approach to improving resiliency and can help guide our ongoing efforts.”
After Winter Storm Mara in February 2023, AE executives directed staff to budget money to conduct an undergrounding feasibility study. In March 2023, the Austin City Council adopted a resolution further directing the utility to study the feasibility of converting existing overhead distribution lines to underground lines (referred to below as Component A).

In April 2023, the Federal Energy Management Agency awarded Austin Energy a Building Resilient Infrastructure and Communities grant to study the resilience of Austin Energy’s overhead distribution system (referred to below as Component B).
These studies are separate, independent initiatives but require much of the same Austin Energy resources to complete. By combining the efforts, the utility will benefit from deliverable results that complement each other, as well as cost savings on internal resources.
For example, if Component A determines undergrounding is prohibitively expensive in one area of the system, Component B may offer an overhead alternative that is more cost effective; yet still increases reliability and resiliency.
Related News
From Archive

- Intrepid Fiber breaks ground on fiber optic network in Superior, Colo.
- Excavator collides with I-95 overpass in Henrico, Va., causing multi-vehicle crash
- Shrewsbury, Mass., expands sewer inspections and cleaning efforts
- Construction worker killed in trench collapse near Prosperity, S.C.
- Two workers rescued after hours trapped in Mich. trench collapse
- WES tunnel boring machine retrieved from Oregon river after seven-month project
- Illinois overhauls Peoples Gas pipeline program, mandates focus on high-risk pipes
- Ameren Illinois to invest $140 million in natural gas pipeline replacement program
- Charlottesville, Va., to begin work on 24-inch water line for Rivanna River crossing
- Mass. governor slams Trump for ‘dangerous delay’ of $50 million in lead pipe replacement funds
Comments