Hartford, Conn., begins $316 million underground transmission upgrade
(UI) — Eversource has started a $315.8 million project to modernize underground power lines in Hartford, replacing 115-kilovolt cables that have been in service since the 1970s, according to Hartford Business.
The Hartford Underground Cable Modernization Project will replace about 7 miles of aging fluid-filled lines with newer solid dielectric XLPE cables, designed to improve reliability and eliminate the risk of oil leaks.
Construction began in April 2025 and is scheduled to finish in late 2026, with the new system expected online by the end of 2027. The Connecticut Siting Council approved the project in June 2024.
The upgrades affect two major links in the city’s grid: the 1,722 Line, which runs 2.9 miles from Northwest to Southwest Hartford substations, and the 1,704 Line, a 3.8-mile segment connecting to South Meadow Substation. Work is being carried out mostly within existing street corridors to limit disruptions.
According to Hartford Business, Eversource says the modernization will cut environmental risks, extend cable life, and make future repairs faster and less disruptive, as maintenance on the new XLPE system can be done in manholes rather than through excavation.
Related News
From Archive
- Oil pipeline struck during fiber optic construction spills into L.A. storm drains
- Utility strike at center of Dallas explosion investigation
- Gas line strike destroys three homes in Ohio neighborhood
- $1 billion Ohio River Tunnel project awarded in Pittsburgh
- Las Vegas advances multibillion-dollar water pipeline expansion
- Final Lake Erie sewer tunnel project set to begin after decades-long $3 billion effort
- Inside Infrastructure: Utility locators warn of systemic failures in damage prevention process
- Senate passes PIPELINE Safety Act aimed at strengthening buried utility protection
- $104 million Lynchburg, Va., tunnel nears breakthrough beneath Blackwater Creek

Comments