Idaho approves burial of Snake River gas pipeline to replace aging span
POCATELLO, Idaho (UI) — The Bureau of Land Management has approved a project to relocate and bury a natural gas pipeline beneath the Snake River near American Falls in southeast Idaho.
Intermountain Gas will remove about 1,500 feet of existing pipeline bridge and install a new six-inch-diameter section of pipe underground to meet growing industrial demand.
The pipeline currently runs across parcels managed by the BLM, Bureau of Reclamation, and Idaho Department of Lands near the BLM Pipeline Campground. Construction is scheduled for the winter months to minimize disruption to recreation, with fewer than three surface acres expected to be affected. Temporary closures of BLM facilities will be required once work begins.
“This pipeline amendment will allow Intermountain Gas to remove the aged infrastructure of the existing pipeline bridge and replace it with an underground pipeline, which would continue to serve natural gas customers,” BLM officials said in a statement.
The project is intended to modernize infrastructure, reduce risks tied to aging aboveground facilities, and support national energy priorities.
According to the BLM, the final environmental assessment, finding of no significant impact, and decision record are available on the agency’s National NEPA Register.
Related News
From Archive
- OSHA investigates fatal trench collapse at Conroe construction site
- Final Lake Erie sewer tunnel project set to begin after decades-long $3 billion effort
- Texas811 launches real-time excavation detection to prevent utility strikes
- Oil pipeline struck during fiber optic construction spills into L.A. storm drains
- Fiber drilling strike triggers major sewer failure, lawsuits in Florida
- Fatal trench collapse in Mass. leads to $4.6 million OSHA penalty, dozens of violations
- Texas811 launches real-time excavation detection to prevent utility strikes
- Race Communications breaks ground on Bakersfield fiber network
- Final Lake Erie sewer tunnel project set to begin after decades-long $3 billion effort
- Inside Infrastructure: Utility locators warn of systemic failures in damage prevention process

Comments