Blasting Underway as Part of Akron’s $1B Sewer Project

AKRON, Ohio (AP) — Officials say contractors started conducting controlled blasts underground in downtown Akron last week as part of work on the Ohio Canal Interceptor Tunnel.
The Akron Beacon Journal reports (http://bit.ly/2gfzoeZ ) the giant underground tunnel is a major component of the northeast Ohio city’s massive $1 billion sewer project to limit overflows into local waterways.
Project officials say the use of explosives became necessary after workers got to the point where the underground rock was too hard to continue digging.
Blasting began Nov. 8 in one of the two shafts in the construction area along the Akron Innerbelt at West Market Street.
Residents within a half-mile radius of blast sites may potentially hear a sound similar to fireworks and feel vibrations when blasts are occurring.
Related News
From Archive

- Intrepid Fiber breaks ground on fiber optic network in Superior, Colo.
- Excavator collides with I-95 overpass in Henrico, Va., causing multi-vehicle crash
- Shrewsbury, Mass., expands sewer inspections and cleaning efforts
- Two workers rescued after hours trapped in Mich. trench collapse
- Trump calls for Keystone XL pipeline revival, but developer has moved on
- Illinois overhauls Peoples Gas pipeline program, mandates focus on high-risk pipes
- Ameren Illinois to invest $140 million in natural gas pipeline replacement program
- Charlottesville, Va., to begin work on 24-inch water line for Rivanna River crossing
- Mass. governor slams Trump for ‘dangerous delay’ of $50 million in lead pipe replacement funds
Comments