AKRON, Ohio (AP) — Officials say contractors started conducting controlled blasts underground in downtown Akron last week as part of work on the Ohio Canal Interceptor Tunnel.
The Akron Beacon Journal reports (http://bit.ly/2gfzoeZ ) the giant underground tunnel is a major component of the northeast Ohio city’s massive $1 billion sewer project to limit overflows into local waterways.
Project officials say the use of explosives became necessary after workers got to the point where the underground rock was too hard to continue digging.
Blasting began Nov. 8 in one of the two shafts in the construction area along the Akron Innerbelt at West Market Street.
Residents within a half-mile radius of blast sites may potentially hear a sound similar to fireworks and feel vibrations when blasts are occurring.
Related News
From Archive
- U.S. water reuse boom to fuel $47 billion in infrastructure spending through 2035
- Major water pipe break in Puerto Rico hits over 165,000 customers
- Potomac River Tunnel project enters construction phase beneath Washington, D.C.
- U.S. Army Corps approves Enbridge's $500 million Line 5 Tunnel project
- Mexico accelerates $6.7 billion water infrastructure plan amid U.S. water disputes
- Glenfarne Alaska LNG targets late-2026 construction start for 807-mile pipeline project
- Pennsylvania American Water launches interactive map to identify, replace lead water service lines
- Trump's tariffs drive $33 million cost increase for Cincinnati sewer project
- CASE Launches New Equipment Configurator At CaseCE.com
- Utah city launches historic $70 million tunnel project using box jacking under active rail line