Delaware Town Loses Building Permit Fee Case to Sewer and Water Company
DOVER, Del. (AP) – A judge has ruled that a central Delaware town cannot collect $27,000 from a local water and sewer authority as a building permit fee for a million-gallon water storage tank.
The judge ruled Monday that the purported building fee demanded by the town of Camden is actually a tax, from which the Camden-Wyoming Sewer and Water Authority is exempt.
In applying for a building permit, the authority sought a waiver of any permit fees. The town refused to waive the fee and issued a stop-work order after the authority did not pay it, leading to a Chancery Court lawsuit.
The judge noted that the $27,000 was intended to support town government in general, as opposed to supporting any licensing or inspection function that might be related to a building permit.
Related News
From Archive
- Oil pipeline struck during fiber optic construction spills into L.A. storm drains
- Utility strike at center of Dallas explosion investigation
- Gas line strike destroys three homes in Ohio neighborhood
- $1 billion Ohio River Tunnel project awarded in Pittsburgh
- Las Vegas advances multibillion-dollar water pipeline expansion
- When and why manhole rehabilitation is critical to sewer system performance
- Inside Infrastructure: Utility locators warn of systemic failures in damage prevention process
- Senate passes PIPELINE Safety Act aimed at strengthening buried utility protection
- $104 million Lynchburg, Va., tunnel nears breakthrough beneath Blackwater Creek

Comments