HDD Activities OK’d at Another Nexus Gas Transmission Site
3/1/2018

FERC has approved Enbridge’s request to move ahead with construction at the Tuscarawas River horizontal directional drill (HDD) site associated with the Nexus Gas Transmission Pipeline.
Last month, the commission approved HDD construction activities at the following 11 sites along the project:
- Wetland (milepost 7.84 – 8.40)
Nimisila Reservoir (milepost 40.87 – 41.20) - East Branch Black River (milepost 87.49 – 87.15)
- West Branch Black River (milepost 93.24 – 92.92)
- Vermilion River (milepost 104.96 – 105.56)
- Interstate 80 (milepost 111.21 – 110.94)
- Huron River (milepost 117.68 – 118.14)
- Sandusky River (milepost 147.19 – 146.70)
- Portage River (milepost 163.72 – 163.38)
- Findlay Road (milepost 181.12 – 180.84)
Maumee River (milepost 182.22 – 182.98)
The Nexus Gas Transmission Pipeline Project includes the construction of an approximately 255-mile interstate natural gas transmission pipeline that will deliver 1.5 billion cubic feet per day of clean-burning natural gas from receipt points in eastern Ohio to existing pipeline system interconnects in southeastern Michigan.
The project is expected to be placed in service later this year.
Related News
From Archive
Sign up to Receive Our Newsletter

- NTSB publishes preliminary report on fatal gas pipeline explosion in Lexington, Mo.
- 290-mile gas pipeline expansion proposed across Georgia, Alabama and South Carolina
- Ripple Fiber breaks ground on $140 million project, expanding into central Mass.
- City of Albuquerque halts fiber optic construction in response to damage, complaints
- Body retrieved day after fatal trench collapse at Bakersfield, Calif., job site
- Gehl and Mustang offer world’s largest skid loader
- Growing Pains and Gains
- Authorities investigating trench collapse that killed worker in Ashburn, Va.
- City of Albuquerque halts fiber optic construction in response to damage, complaints
- Pasadena, Calif., undergrounding project could take 500 years to finish
Comments