Developers Seek Extension for Constitution Pipeline

ALBANY, N.Y. (AP) — Constitution Pipeline Company is asking federal regulators for more time to build a 124-mile natural gas pipeline from Pennsylvania’s shale fields to eastern New York.
The Federal Energy Regulatory Commission approved a permit for the pipeline in December 2014 on condition of getting a state water quality permit and completing work by December 2016. But New York’s Department of Environmental Conservation denied the state permit in April, saying it failed to meet standards to protect streams and other water resources.
The company has appealed the permit denial to the U.S. Circuit Court of Appeals, arguing that the state’s refusal is arbitrary and capricious.
In a letter to FERC on Friday, the developers asked to have the completion time extended to December 2018 while it pursues legal action.
Related News
From Archive

- 290-mile gas pipeline expansion proposed across Georgia, Alabama and South Carolina
- City of Albuquerque halts fiber optic construction in response to damage, complaints
- Body retrieved day after fatal trench collapse at Bakersfield, Calif., job site
- $227 million Garnet Valley water project advances, set to create 73,000 jobs in Nevada
- Pasadena, Calif., undergrounding project could take 500 years to finish
- Gehl and Mustang offer world’s largest skid loader
- Growing Pains and Gains
- Authorities investigating trench collapse that killed worker in Ashburn, Va.
- City of Albuquerque halts fiber optic construction in response to damage, complaints
- Pasadena, Calif., undergrounding project could take 500 years to finish
Comments