Judge Orders Temporary Stop on Dakota Access Pipeline Construction in North Dakota

WASHINGTON (AP) — An American Indian tribe succeeded Tuesday in getting a federal judge to temporarily stop construction on some, but not all, of a $3.8 billion four-state oil pipeline, but its broader request still hangs in the balance.
U.S. District Judge James Boasberg said Tuesday that work will temporarily stop between North Dakota’s State Highway 1806 and 20 miles east of Lake Oahe, but will continue west of the highway because he believes the U.S. Army Corps of Engineers lacks jurisdiction on private land.
He also said he will rule by the end of Friday on the Standing Rock Sioux Tribe’s challenge of federal regulators’ decision to grant permits to the Dallas-based operators of the Dakota Access Pipeline, which will cross North Dakota, South Dakota, Iowa and Illinois.
A weekend confrontation between protesters and construction workers near Lake Oahe prompted the tribe to ask Sunday for a temporary stop of construction. Four private security guards and two guard dogs received medical treatment, officials said, while a tribal spokesman noted that six people — including a child — were bitten by the dogs and at least 30 people were pepper-sprayed.
Related News
From Archive

- 2 workers killed, 1 injured while working on sewer line in Mobile, Ala.
- $5.3 billion, 516-mile pipeline to connect Texas to Arizona through New Mexico
- Tunnel boring continues under Chesapeake Bay for $3.9 billion HRBT Expansion project
- Judge approves construction for key portion of $485 million pipeline in Larimer County, Colo.
- 31 workers rescued after LA tunnel partially collapses
- New products: Latest industry developments
- 31 workers rescued after LA tunnel partially collapses
- Ohio Supreme Court rules sewer line location isn’t a ‘defect’ in property dispute
- Faulconer Construction begins rock blasting for water pipeline project in Charlottesville, Va.
- $5.3 billion, 516-mile pipeline to connect Texas to Arizona through New Mexico
Comments