HDD Activities Get Green Light at More Rover Pipeline Locations
FERC has conditionally approved Energy Transfer Partners’ request to resume horizontal directions drilling (HDD) activities at the following locations along the Rover Pipeline:
- Honey Creek – Energy Transfer Partners says J.D. Hair & Associates’
recommendation of using an 8-degree overbend is not feasible, and that increasing the exit angle and breakover height is not possible due to safety concerns associated with overhead power lines. Due to these constraints and J.D. Hair & Associates’ review, FERC recommends maintaining the original 2.5-degree overbend to 6-degree exit angle. - Interstate Highway 77
- Ohio River Majorsville
- Norfolk Southern Railroad – Revision 0 of the design drawing for Line B, dated July 7, 2017, incorporates Geo-Engineers recommended design modifications by increasing the entry/exit angles from 8 degrees to 11 degrees on the east side and from 14 degrees to 15 degrees on the west side, and dropping the bottom design tangent by 10 feet. Based on input from J.D. Hair & Associates, these recommendations should reduce the risk of HDD operational problems associated with drilling within the bedrock-transition zone.
The Rover Pipeline Project includes a new interstate pipeline and related facilities extending from the Appalachian supply area to a proposed interconnection with Vector Pipeline, LP in Livingston County, Michigan. It will transport up to 3.25 billion cubic feet per day of domestically-produced natural gas to markets in the Midwest, Northeast, East Coast, Gulf Coast and Canada, with direct deliveries to Ohio, West Virginia, Michigan, and into the Dawn Hub in Ontario, Canada, which includes a broader network of distribution points back into the U.S.
The project is expected to be placed in service in November 2017.
Related News
From Archive
- PHMSA warns of heat risks in aging plastic gas distribution pipelines following deadly Pennsylvania explosion
- OSHA seeks $1.2 million fine after fatal trench collapse in Connecticut
- Phase 1 Alaska LNG pipeline advances with construction awards, pipe supply agreements
- OSHA issues 16 citations following fatal sewer confined space incident
- Gateway Tunnel construction faces shutdown next week as Trump withholds federal funding
- T-Mobile to expand fiber broadband infrastructure footprint with $4.9 billion Metronet acquisition
- First tunnel boring machines complete testing for Hudson Tunnel Project
- NWPX grows water infrastructure portfolio with Colorado precast facility
- Cityside launches $100 million fiber build in Corona, Calif.
- FiberLight to build 1,400-mile West Texas dark fiber network in $350 million expansion

Comments