Increased Water Pumping Worries Line 3 Pipeline Opponents
(AP) — Opponents of Enbridge Energy’s Line 3 oil pipeline project are worried about the potential impact of the company’s plan to temporarily pump as much as 10 times more groundwater out of the construction area than once planned.
Enbridge originally got permission to pump about 510 million gallons (1.9 billion liters) of water from the trenches it’s digging as it replaces the current, aging Line 3 pipeline along a partly new, 340-mile (545-kilometer) route across northern Minnesota.
But the Calgary, Alberta-based company encountered more groundwater than it anticipated, and earlier this month it obtained a permit from the Minnesota Department of Natural Resources to pump up to nearly 5 billion gallons (18.9 billion liters) for the remaining 145 miles (230 kilometers) of pipeline it has left to build, Minnesota Public Radio reported Thursday.
Indigenous and environmentalist groups fighting the project say the pumping could affect groundwater quality and sensitive wetlands, lakes and streams along the route — including culturally and economically important wild rice beds — which are already stressed by drought.
“Given that we find ourselves in a moderate drought, with higher than average temperatures and lower than average precipitation, displacing this amount of water will have a direct detrimental impact on the 2021 wild rice crop,” wrote Michael Fairbanks and Alan Roy, tribal chairman and secretary-treasurer of the White Earth Nation.
But the Department of Natural Resources says it determined that the increased pumping won’t threaten groundwater sustainability or have other harmful impacts on natural resources.
The agency’s permit allows Enbridge to pump shallow groundwater only from the construction area, not from lakes or wetlands, said Randall Doneen, a senior department administrator who oversees ecological and water resources. The water is temporarily stored and treated, then discharged nearby, where it soaks back into the ground, he said.
Enbridge spokeswoman Juli Kellner attributed the need to pump more water in part to the company’s decision to use more wellpoint systems — a series of wells installed along the excavated trench that lower the shallow groundwater.
Wellpoints produce cleaner water with less dirt and sediment than using traditional sump pumps to get water out of the trench, said Kelton Barr, a consulting hydrogeologist who’s not involved in Line 3.
Enbridge’s permit specifies that water removed from the construction trench cannot be discharged directly into a surface waterway, such as a lake or wetland. It must be run through a large fabric bag that filters out sediment before the water is discharged into well-vegetated upland areas or constructed stormwater ponds.
Related News
From Archive
- OSHA issues 16 citations following fatal sewer confined space incident
- 27 pipeline safety violations tied to deadly Pa. chocolate factory explosion
- Contractor gas line strike triggers home explosion in Missouri
- LA recovery reports call for $650 million power line burial, major utility upgrades in Pacific Palisades
- Comprehensive microtrenching FAQ: Key insights on the Vermeer MTR516 microtrencher
- T-Mobile to expand fiber broadband infrastructure footprint with $4.9 billion Metronet acquisition
- First tunnel boring machines complete testing for Hudson Tunnel Project
- NWPX grows water infrastructure portfolio with Colorado precast facility
- Cityside launches $100 million fiber build in Corona, Calif.
- FiberLight to build 1,400-mile West Texas dark fiber network in $350 million expansion

Comments