San Diego sewer upgrade nears completion, potholing to confirm underground utilities
9/12/2024
(UI) — Construction work on the AC Water and Sewer Group 1048 project is nearing completion on Governor Drive, with crews finishing the installation of sewer mains and laterals.
The next phase of the project is set to begin on Edmonton Ave., Combe Way, and Stettler Way, near Curie Elementary School, starting June 7.
The upcoming work will replace sewer mains and laterals on the three streets. Before heavy construction begins, a drone will be used to document existing conditions of the streets, sidewalks, and nearby private properties.
Crews will also conduct potholing to verify the locations of underground pipes and utility lines. This phase of the project is expected to wrap up before the start of the 2024-25 school year.
Related News
From Archive
Sign up to Receive Our Newsletter
- Fatal trench collapse halts sewer construction in Massachusetts; two workers hospitalized
- Alaska LNG pipeline could require 7,000 workers at peak construction, developers say
- Ohio trench collapse kills one worker, injures two during pipe installation
- Elon Musk's Boring Co. fined for dumping drilling waste into Vegas sewer system
- $1.4 billion Midwest pipeline expansion to move more Canadian oil to U.S. Gulf
- Glenfarne Alaska LNG targets late-2026 construction start for 807-mile pipeline project
- Fatal trench collapse halts sewer construction in Massachusetts; two workers hospitalized
- Massive water line failure leaves majority of Waterbury without service
- Infrastructure failure releases 100,000 gallons of wastewater in Houston; repairs ongoing
- Pennsylvania American Water launches interactive map to identify, replace lead water service lines

Comments