(UI) — Construction work on the AC Water and Sewer Group 1048 project is nearing completion on Governor Drive, with crews finishing the installation of sewer mains and laterals.
The next phase of the project is set to begin on Edmonton Ave., Combe Way, and Stettler Way, near Curie Elementary School, starting June 7.
The upcoming work will replace sewer mains and laterals on the three streets. Before heavy construction begins, a drone will be used to document existing conditions of the streets, sidewalks, and nearby private properties.
Crews will also conduct potholing to verify the locations of underground pipes and utility lines. This phase of the project is expected to wrap up before the start of the 2024-25 school year.
Related News
From Archive
Sign up to Receive Our Newsletter
- Inside Sempra’s 72-mile pipeline with 18 major trenchless crossings
- Trump vetoes bill to finish $1.3 billion Colorado water pipeline
- PHMSA warns of heat risks in aging plastic gas distribution pipelines following deadly Pennsylvania explosion
- Infrastructure failure releases 100,000 gallons of wastewater in Houston; repairs ongoing
- OSHA seeks $1.2 million fine after fatal trench collapse in Connecticut
- Worm-like robot burrows underground to cut power line installation costs
- First tunnel boring machines complete testing for Hudson Tunnel Project
- Infrastructure failure releases 100,000 gallons of wastewater in Houston; repairs ongoing
- Construction jobs stumble into 2026 after weak year
- NWPX grows water infrastructure portfolio with Colorado precast facility

Comments