Stuck Tunneling Rig to Cost Omaha $2.75M for Sewer Project
1/30/2017
OMAHA, Neb. (AP) – Omaha will have to pay $2.75 million extra to complete one of its sewer overhaul projects because a tunnel boring machine got stuck.
The Omaha World-Herald reports that the machine was 70 feet underground between the downtown Heartland of America Park and the Missouri River when it ran into boulders and watery gravel.
It had to stop 900 feet short of its destination.
The City Council has agreed to pay the contractor for digging a shaft down to the machine and taking it out and then pay for the lowering of a heavier duty drilling rig into the tunnel to finish the work.
The project now is expected to be delayed at least until the end of his year – about one year later than the original completion date.
Related News
From Archive
Sign up to Receive Our Newsletter
- OSHA issues 16 citations following fatal sewer confined space incident
- 27 pipeline safety violations tied to deadly Pa. chocolate factory explosion
- Contractor gas line strike triggers home explosion in Missouri
- LA recovery reports call for $650 million power line burial, major utility upgrades in Pacific Palisades
- Comprehensive microtrenching FAQ: Key insights on the Vermeer MTR516 microtrencher
- T-Mobile to expand fiber broadband infrastructure footprint with $4.9 billion Metronet acquisition
- First tunnel boring machines complete testing for Hudson Tunnel Project
- NWPX grows water infrastructure portfolio with Colorado precast facility
- Cityside launches $100 million fiber build in Corona, Calif.
- FiberLight to build 1,400-mile West Texas dark fiber network in $350 million expansion

Comments