Stuck Tunneling Rig to Cost Omaha $2.75M for Sewer Project
1/30/2017

OMAHA, Neb. (AP) – Omaha will have to pay $2.75 million extra to complete one of its sewer overhaul projects because a tunnel boring machine got stuck.
The Omaha World-Herald reports that the machine was 70 feet underground between the downtown Heartland of America Park and the Missouri River when it ran into boulders and watery gravel.
It had to stop 900 feet short of its destination.
The City Council has agreed to pay the contractor for digging a shaft down to the machine and taking it out and then pay for the lowering of a heavier duty drilling rig into the tunnel to finish the work.
The project now is expected to be delayed at least until the end of his year – about one year later than the original completion date.
Related News
From Archive
Sign up to Receive Our Newsletter

- Intrepid Fiber breaks ground on fiber optic network in Superior, Colo.
- Excavator collides with I-95 overpass in Henrico, Va., causing multi-vehicle crash
- Shrewsbury, Mass., expands sewer inspections and cleaning efforts
- Two workers rescued after hours trapped in Mich. trench collapse
- Trump calls for Keystone XL pipeline revival, but developer has moved on
- Illinois overhauls Peoples Gas pipeline program, mandates focus on high-risk pipes
- Ameren Illinois to invest $140 million in natural gas pipeline replacement program
- Charlottesville, Va., to begin work on 24-inch water line for Rivanna River crossing
- Mass. governor slams Trump for ‘dangerous delay’ of $50 million in lead pipe replacement funds
Comments