Akron Cites Savings as Massive Sewer Project Proceeds

AKRON, Ohio (AP) — Officials say a $1.1 billion Akron water and sewer project is under budget as work that includes a massive underground tunnel continues.
The Akron Beacon Journal reports (http://bit.ly/2jP3A2J ) a drill will begin cutting a 27-foot circle this July for a tunnel just over a mile long.
The tunnel is a major component of the northeastern Ohio city’s project meant to limit overflows into local waterways. The cost is about $300 million below original estimates.
Engineers say none of the city’s estimated annual 742 million gallons of wastewater-rain mix will touch the Little Cuyahoga (ky-uh-HOH’-guh) River by the project’s court-ordered completion in 2028.
The project will combine the new tunnel and other smaller tunnels with green components such as porous asphalt and wetlands.
Related News
From Archive

- 290-mile gas pipeline expansion proposed across Georgia, Alabama and South Carolina
- $227 million Garnet Valley water project advances, set to create 73,000 jobs in Nevada
- Pasadena, Calif., undergrounding project could take 500 years to finish
- Construction underway for $1.4 billion, 60-mile water pipeline in Chicago
- HDD industry faces challenges as cities push back on fiber drilling disruptions
- Gehl and Mustang offer world’s largest skid loader
- Growing Pains and Gains
- Authorities investigating trench collapse that killed worker in Ashburn, Va.
- Pasadena, Calif., undergrounding project could take 500 years to finish
- $227 million Garnet Valley water project advances, set to create 73,000 jobs in Nevada