COLUMBUS, Ohio (AP) — Ohio’s environmental regulators have issued a $430,000 fine against a company building a natural gas pipeline from West Virginia to Michigan.
The Ohio Environmental Protection Agency says the fines stem from water and air pollution violations at a number of locations.
State officials say work on the Rover natural gas pipeline since March has resulted in 18 incidents involving mud spills from drilling, stormwater pollution and open burning.
Energy Transfer is the company building the $4.2 billion pipeline. It will carry gas from West Virginia, western Pennsylvania and eastern Ohio.
A company spokesman tells The Columbus Dispatch (http://bit.ly/2qNCMCS ) that a small number of inadvertent releases of ‘drilling mud’ aren’t unusual during drilling operations.
He also said Monday that the company doesn’t think there has been any impact to the environment.
Related News
From Archive
- PHMSA warns of heat risks in aging plastic gas distribution pipelines following deadly Pennsylvania explosion
- OSHA seeks $1.2 million fine after fatal trench collapse in Connecticut
- Phase 1 Alaska LNG pipeline advances with construction awards, pipe supply agreements
- OSHA issues 16 citations following fatal sewer confined space incident
- Gateway Tunnel construction faces shutdown next week as Trump withholds federal funding
- T-Mobile to expand fiber broadband infrastructure footprint with $4.9 billion Metronet acquisition
- First tunnel boring machines complete testing for Hudson Tunnel Project
- Construction jobs stumble into 2026 after weak year
- NWPX grows water infrastructure portfolio with Colorado precast facility
- Cityside launches $100 million fiber build in Corona, Calif.

Comments