Judge Refuses to Delay Hearing on Pipeline Land Acquisition
HARRISONBURG, Va. (AP) — A federal judge has refused to postpone a hearing in a lawsuit brought by developers seeking possession of land in several Virginia counties for a controversial pipeline project.
Atlantic Coast Pipeline is seeking possession of several properties in Augusta, Bath, Buckingham and Cumberland counties for the natural gas pipeline, which would run through West Virginia, Virginia and North Carolina.
The judge declined Monday to postpone a Feb. 26 hearing regarding land in Bath County, but he ordered developers to turn over more information and gave property owners more time to respond. Disputes over land in other counties also will be addressed at next Monday’s hearing.
Developers say federal environmental regulations require completion of any tree felling by March 14, and that missing that deadline would push back construction until November.
Related News
From Archive
- Inside Sempra’s 72-mile pipeline with 18 major trenchless crossings
- Trump vetoes bill to finish $1.3 billion Colorado water pipeline
- PHMSA warns of heat risks in aging plastic gas distribution pipelines following deadly Pennsylvania explosion
- Infrastructure failure releases 100,000 gallons of wastewater in Houston; repairs ongoing
- OSHA seeks $1.2 million fine after fatal trench collapse in Connecticut
- Worm-like robot burrows underground to cut power line installation costs
- First tunnel boring machines complete testing for Hudson Tunnel Project
- Infrastructure failure releases 100,000 gallons of wastewater in Houston; repairs ongoing
- Construction jobs stumble into 2026 after weak year
- NWPX grows water infrastructure portfolio with Colorado precast facility

Comments