Phase 1 of 650-Mile NGL Pipeline Done
EPIC Y Grade Pipeline, LP, a subsidiary of EPIC Y Grade Services, LP and EPIC Midstream Holdings, LP, has placed Phase 1 of its 650-mile NGL pipeline, which connects DLK Black River Midstream’s processing plant in Eddy County, N.M., and Delaware Basin Midstream’s terminal in Orla County, Texas, in service.
Once finished, the pipeline will have throughput capacity of 350,000 bpd with multiple origin points in the Delaware and Midland Basins, including interconnects in Orla, Benedum and Corpus Christi, Texas, where the company is constructing a fractionation complex to accommodate the pipeline’s volume. It will run side by side with the company’s 730-mile EPIC crude oil pipeline, which will deliver approximately 550,000 bpd from the Permian and Eagle Ford Basins to refining and export markets worldwide. day from the Delaware and Midland basins.
According to EPIC, NGL was introduced to the pipeline on March 12, and Phase 2 is currently under construction with a projected in-service date of June. Phase 3 of the project is expected to be completed in the second-half of 2019.
Related News
From Archive
- OSHA issues 16 citations following fatal sewer confined space incident
- 27 pipeline safety violations tied to deadly Pa. chocolate factory explosion
- Contractor gas line strike triggers home explosion in Missouri
- LA recovery reports call for $650 million power line burial, major utility upgrades in Pacific Palisades
- Comprehensive microtrenching FAQ: Key insights on the Vermeer MTR516 microtrencher
- T-Mobile to expand fiber broadband infrastructure footprint with $4.9 billion Metronet acquisition
- First tunnel boring machines complete testing for Hudson Tunnel Project
- NWPX grows water infrastructure portfolio with Colorado precast facility
- Cityside launches $100 million fiber build in Corona, Calif.
- FiberLight to build 1,400-mile West Texas dark fiber network in $350 million expansion

Comments