APA Group Completes Gas Pipeline, Brisbane River Crossing
(UC) — APA Group said it has completed the installation of a gas pipeline in Australia that included a 300-foot (905-meter) crossing under the Brisbane River.
APA contracted Diona Civil Engineering Contractors, with additional support from Coe Drilling, for the pipeline installation, completed at a depth of 33 feet (10 meters) below the river, as part of the Murarrie Looping Project.
The horizontal directional drill (HDD) and pipe pull involved a 500-ton drill rig, two franna cranes and six excavators. It was completed over 24 hours using 70 workers.
During installation, 300 feet of DN 300 gas pipe was pulled under the Brisbane river with detailed planning in design and methodology required to ensure accuracy of the alignment installation.
The new 300 mm high-pressure steel pipeline is a duplication of the Murarrie Pipeline, which provides gas to more than 88,000 customers.
Related News
From Archive
- Fatal trench collapse halts sewer construction in Massachusetts; two workers hospitalized
- Alaska LNG pipeline could require 7,000 workers at peak construction, developers say
- Ohio trench collapse kills one worker, injures two during pipe installation
- Elon Musk's Boring Co. fined for dumping drilling waste into Vegas sewer system
- $1.4 billion Midwest pipeline expansion to move more Canadian oil to U.S. Gulf
- Glenfarne Alaska LNG targets late-2026 construction start for 807-mile pipeline project
- Fatal trench collapse halts sewer construction in Massachusetts; two workers hospitalized
- Massive water line failure leaves majority of Waterbury without service
- Infrastructure failure releases 100,000 gallons of wastewater in Houston; repairs ongoing
- Pennsylvania American Water launches interactive map to identify, replace lead water service lines

Comments