APA Group Completes Gas Pipeline, Brisbane River Crossing
(UC) — APA Group said it has completed the installation of a gas pipeline in Australia that included a 300-foot (905-meter) crossing under the Brisbane River.
APA contracted Diona Civil Engineering Contractors, with additional support from Coe Drilling, for the pipeline installation, completed at a depth of 33 feet (10 meters) below the river, as part of the Murarrie Looping Project.
The horizontal directional drill (HDD) and pipe pull involved a 500-ton drill rig, two franna cranes and six excavators. It was completed over 24 hours using 70 workers.
During installation, 300 feet of DN 300 gas pipe was pulled under the Brisbane river with detailed planning in design and methodology required to ensure accuracy of the alignment installation.
The new 300 mm high-pressure steel pipeline is a duplication of the Murarrie Pipeline, which provides gas to more than 88,000 customers.
Related News
From Archive

- Intrepid Fiber breaks ground on fiber optic network in Superior, Colo.
- Excavator collides with I-95 overpass in Henrico, Va., causing multi-vehicle crash
- Shrewsbury, Mass., expands sewer inspections and cleaning efforts
- Construction worker killed in trench collapse near Prosperity, S.C.
- Two workers rescued after hours trapped in Mich. trench collapse
- WES tunnel boring machine retrieved from Oregon river after seven-month project
- Illinois overhauls Peoples Gas pipeline program, mandates focus on high-risk pipes
- Ameren Illinois to invest $140 million in natural gas pipeline replacement program
- Charlottesville, Va., to begin work on 24-inch water line for Rivanna River crossing
- Mass. governor slams Trump for ‘dangerous delay’ of $50 million in lead pipe replacement funds
Comments