PAUL, Minn. (AP) — Minnesota regulators say there have been more releases of drilling fluid along the Line 3 oil pipeline construction route than previously reported.
According to the Minnesota Pollution Control Agency, there were 28 releases at 12 river crossing locations from June 8 to Aug. 5. In one instance, on July 6, about 80 gallons of fluid entered the Willow River in Aitkin County.
The MPCA also says there were 13 spills into wetlands and 14 accidental releases in upland areas, although one of those flowed into a wetland.
The agency disclosed details about the releases on Aug. 9 in a letter to Democratic state lawmakers who had requested the information, Minnesota Public Radio reported Aug. 10.
Drilling fluid is used as a lubricant. It’s made mostly of bentonite clay and water, and is not considered toxic, but can impact aquatic life.
The agency said Enbridge’s permit does not authorize the release of drilling fluid to wetlands or rivers. It says the releases are under investigation as potential violations.
Enbridge said in a statement that the drilling mud was quickly contained and cleaned up in the vast majority of instances under the supervision of trained environmental inspectors and independent monitors, and that the spills were reported to state regulators.
Line 3 construction across northern Minnesota is more than 80% complete and remains on pace to finish in the fourth quarter, the company said.
Enbridge said its practice of horizontal directional drilling is the preferred construction method for pipelines crossing under bodies of water, and that it actually protects waterbodies from disturbance. Drilling operations are immediately shut down when spills occur and state regulators are notified, it said.
Related News
From Archive
- OSHA issues 16 citations following fatal sewer confined space incident
- 27 pipeline safety violations tied to deadly Pa. chocolate factory explosion
- Contractor gas line strike triggers home explosion in Missouri
- LA recovery reports call for $650 million power line burial, major utility upgrades in Pacific Palisades
- Comprehensive microtrenching FAQ: Key insights on the Vermeer MTR516 microtrencher
- T-Mobile to expand fiber broadband infrastructure footprint with $4.9 billion Metronet acquisition
- First tunnel boring machines complete testing for Hudson Tunnel Project
- NWPX grows water infrastructure portfolio with Colorado precast facility
- Cityside launches $100 million fiber build in Corona, Calif.
- FiberLight to build 1,400-mile West Texas dark fiber network in $350 million expansion

Comments