Idaho-Wyoming gas pipeline needs environmental study for approval
BOISE, Idaho (AP) — U.S. officials won’t approve a natural gas pipeline from Idaho to Wyoming until additional environmental studies are completed.
A U.S. District Court last week approved an agreement between the U.S. Forest Service and two environmental groups that filed a lawsuit to stop the 50-mile (80-kilometer) Crow Creek Pipeline Project.
The Forest Service agreed to complete a supplemental environmental impact statement before authorizing the project that partially crosses Forest Service land. The timeline for completing the environmental study isn’t clear.
Wyoming-based Lower Valley Energy wants to build the pipeline that would start near Montpelier, Idaho, and run to Afton, Wyoming. But the Alliance for the Wild Rockies and Yellowstone to Uintas Connection say it will harm protected grizzly bears and other wildlife.
“The ruling is a huge victory for the climate as well as free-roaming endangered species like grizzly bears, wolverines, and lynx,” said Mike Garrity, executive director of the Alliance for the Wild Rockies.
A lawsuit the groups filed in 2020 contended an 18-mile (29-kilometer) portion of the pipeline would cut a corridor through Caribou-Targhee National Forest and create a road through six roadless areas. The 2001 Roadless Rule prevents road construction and timber harvest in designated roadless areas, which are typically 5,000 acres (2,000 hectares) or larger.
The environmental groups argued the pipeline corridor would be a permanent motorized trail through the roadless areas.
“This unique area that links the Northern and Southern Rocky Mountains must be protected and managed as a wildlife corridor for our endangered wildlife species,” said Jason Christensen, director of Yellowstone to Uintas Connection.
Lower Valley Energy — which intervened in the case on the side of the Forest Service, as did the state of Wyoming — has previously said it has been trucking natural gas to Afton, but that delivery has been unreliable and the town has sometimes nearly run out.
Lower Valley Energy spokesman Brian Tanabe didn’t immediately return a call Wednesday from The Associated Press.
The Forest Service, before the lawsuit, approved building the pipeline through the forest with a temporary 50-foot (15-meter) wide right-of-way for construction and then a 20-foot (6-meter) utility corridor as a permanent right-of-way. In all, the construction phase would use about 110 acres (45 hectares) of forest land and the permanent right-of-way about 45 acres (18 hectares).
About 26 miles (40 kilometers) of the pipeline crosses private land and about 4 miles (6 kilometers) crosses state land.
Related News
From Archive
- OSHA issues 16 citations following fatal sewer confined space incident
- 27 pipeline safety violations tied to deadly Pa. chocolate factory explosion
- Contractor gas line strike triggers home explosion in Missouri
- LA recovery reports call for $650 million power line burial, major utility upgrades in Pacific Palisades
- Comprehensive microtrenching FAQ: Key insights on the Vermeer MTR516 microtrencher
- T-Mobile to expand fiber broadband infrastructure footprint with $4.9 billion Metronet acquisition
- First tunnel boring machines complete testing for Hudson Tunnel Project
- NWPX grows water infrastructure portfolio with Colorado precast facility
- Cityside launches $100 million fiber build in Corona, Calif.
- FiberLight to build 1,400-mile West Texas dark fiber network in $350 million expansion

Comments