Federal court dismisses challenge to Mountain Valley Pipeline construction
CHARLESTON, W.Va. (AP) — A federal appeals court on Friday granted a motion to dismiss a challenge to construction permits for a controversial natural gas pipeline in Virginia and West Virginia after Congress mandated that the project move forward.

The 4th U.S. Circuit Court of Appeals in Richmond, Virginia, sided with lawyers from Mountain Valley Pipeline in dismissing challenges to the project by environmental groups over concerns about the pipeline’s impact on endangered species, erosion and stream sedimentation.
The U.S. Supreme Court last month allowed construction to resume. Work had been blocked by the 4th Circuit, even after Congress ordered the project’s approval as part of the bipartisan bill to increase the debt ceiling. President Joe Biden signed the bill into law in June.
Lawyers for the company building the 300-mile (500-kilometer) pipeline argued before the appeals court two weeks ago that Congress was within its rights to strip the 4th Circuit from jurisdiction over the case. They also said that any debate over the law’s constitutionality should be heard not by the 4th Circuit but by an appellate court in Washington, because the law passed by Congress spells out that precise scenario.
“Armed with this new legislation enacted specifically in their favor, Respondents — the federal agencies and the Mountain Valley Pipeline — moved in this Court for the dismissal of the petitions,” appeals judge James Wynn wrote. “Upon consideration of the matters before us, we must grant Respondents’ motions to dismiss.”
Environmental groups have opposed the $6.6 billion project, designed to meet growing energy demands in the South and Mid-Atlantic by transporting gas from the Marcellus and Utica fields in Pennsylvania and Ohio.
Related News
From Archive

- Authorities investigating trench collapse that killed worker in Ashburn, Va.
- NTSB publishes preliminary report on fatal gas pipeline explosion in Lexington, Mo.
- Mass. governor slams Trump for ‘dangerous delay’ of $50 million in lead pipe replacement funds
- Ditch Witch West sells first Bulldog trencher to speed up undergrounding work along West Coast
- Centuri awarded nearly $400 million for U.S. gas infrastructure work
- Maryland lawmakers push to curb BGE pipeline spending, citing safety and cost concerns
- Charlottesville, Va., to begin work on 24-inch water line for Rivanna River crossing
- Mass. governor slams Trump for ‘dangerous delay’ of $50 million in lead pipe replacement funds
- City of Albuquerque halts fiber optic construction in response to damage, complaints
- Pasadena, Calif., undergrounding project could take 500 years to finish
Comments