Tampa, Fla., to embark on “historic” infrastructure overhaul
(UI) – On Wednesday, May 1, the city of Tampa, Fla., announced its “biggest infrastructure overhaul in its history.” The investment includes stormwater improvement projects, hundreds of miles of new or repaired water and wastewater pipes, and much more.

In 2019, a nearly $3 billion PIPES Program was approved to make critical repairs and upgrades to Tampa's aging water and wastewater systems. After nearly 10 years without a utility rate increase, PIPES established a schedule of gradual rate increases for water and wastewater services over a 20-year period, providing the funding the city needed to reinvest in its aging water infrastructure.
Over the past five years, more than $800 million has been invested in projects designed to upgrade Tampa's water and wastewater systems. Another $250 million has gone toward stormwater projects, improving drainage and reducing dangerous street flooding. Between the three departments, approximately 300 miles of pipes have been repaired or replaced.
New facilities have been added, technologies have been upgraded to improve operations and efficiency, and new pump stations have come online. In May, the Tampa Water Department partially activated its new High Service Pump Station at the David L. Tippin Water Treatment Plant. The $94 million project replaces aging pumps scattered across the facility, some of which are almost 100 years old. A large portion of Tampa's drinking water will travel through the High Service Pump Station and to the faucets of thousands of homes and businesses.
Tampa also has the third longest wastewater microtunnel in the country. Running 60 ft underground, the new pipe replaces one originally placed into service in 1951. The underground tunnel carries approximately 30% of Tampa's wastewater from a pumping station near the Tampa Riverwalk to the Wastewater Treatment Facility at Port Tampa Bay.
Later this year, construction is expected to conclude for the first of a series of flood relief projects in Tampa's Lower Peninsula. Designed to improve drainage in the region, the first phase also includes the creation of a new park, which will also provide stormwater benefits.
"When historians write about this era of Tampa history, they will tell our grandchildren this was a period when city leaders fully understood infrastructure is the lifeblood of any city," said Mayor Jane Castor.
Related News
From Archive

- HDD industry faces challenges as cities push back on fiber drilling disruptions
- 2 workers killed, 1 injured while working on sewer line in Mobile, Ala.
- $5.3 billion, 516-mile pipeline to connect Texas to Arizona through New Mexico
- Tunnel boring continues under Chesapeake Bay for $3.9 billion HRBT Expansion project
- Judge approves construction for key portion of $485 million pipeline in Larimer County, Colo.
- New products: Latest industry developments
- 31 workers rescued after LA tunnel partially collapses
- Ohio Supreme Court rules sewer line location isn’t a ‘defect’ in property dispute
- Faulconer Construction begins rock blasting for water pipeline project in Charlottesville, Va.
- $5.3 billion, 516-mile pipeline to connect Texas to Arizona through New Mexico
Comments