TC Energy to repair ruptured NGTL natural gas pipeline segment in Canada following wildfires
(UI) – On April 16, TC Energy reported an “incident” at its NOVA Gas Transmission Ltd (NGTL) natural gas system approximately 40 km northwest of Edson, Alta in Yellowhead County, Alberta. According to the company, a rupture occurred on a segment of the system, sparking an “initial ignition” and shutting down the portion of the pipeline.

A secondary fire sparked the following day, which was eventually contained and confirmed by Alberta Wildfire. TC Energy said it’s working with federal regulators to investigate the cause of the rupture and conduct environmental impact studies.
While a portion of the pipeline is shut down, TC Energy assured that NGTL’s “web-like pipeline structure provides many paths for gas transportation access, which allows for operational flexibility.”
Pipeline segments near the rupture have resumed normal operations as of April 22 after completing integrity assessme.ts. TC Energy has now entered the repairing and restoration stage of reconstruction after staying down the initial emergency response.
TC Energy’s 15,153-mile NGTL pipeline system connects most of Western Canada’s natural gas production from the Sedimentary basin to domestic and export markets.
Related News
From Archive

- Authorities investigating trench collapse that killed worker in Ashburn, Va.
- NTSB publishes preliminary report on fatal gas pipeline explosion in Lexington, Mo.
- Mass. governor slams Trump for ‘dangerous delay’ of $50 million in lead pipe replacement funds
- Ditch Witch West sells first Bulldog trencher to speed up undergrounding work along West Coast
- Centuri awarded nearly $400 million for U.S. gas infrastructure work
- Maryland lawmakers push to curb BGE pipeline spending, citing safety and cost concerns
- Charlottesville, Va., to begin work on 24-inch water line for Rivanna River crossing
- Mass. governor slams Trump for ‘dangerous delay’ of $50 million in lead pipe replacement funds
- City of Albuquerque halts fiber optic construction in response to damage, complaints
- Pasadena, Calif., undergrounding project could take 500 years to finish
Comments