Virginia builds $18 million stormwater vault system to mitigate flooding
(UI) – According to the Water Environment Federation’s Stormwater Report (WEF Stormwater Report), Virginia’s Arlington County built a stormwater vault system beneath an elementary school to “mitigate the major impacts of flooding.”
The stormwater vaults, constructed underneath Cardinal Elementary School in the county’s Torreyson Run Watershed, are capable of holding over 15 million liters of water, making it “one of the largest precast concrete stormwater vaults in the Mid-Atlantic,” WEF Stormwater Report said.
Flooding from a summer 2019 storm that devastated the area turn what was supposed to be a small vault into a two-part, $18 million stormwater project that took two years to complete. The first phase of construction involved laying underground pipes and junction boxes to redirect water from a previously-installed storm sewer beneath the elementary school to the new vault location. The second phase included the physical vault construction, which ended summer 2023.
A 7-ft. underground pipe carries water to the vaults. After a few hours, gravity brings said water out of the vault and into a designated drainage site. Heavy rainfall in August 2023 put the vault system to the test with success, WEF Stormwater Report acknowledged.
The project is part of the greater "Flood Resilient Arlington" program. According to the government website, Arlington’s stormwater system includes 10,000 storm drains and more than 330 miles of storm sewers.
This story was originally reported by WEF Stormwater Report.
Related News
From Archive

- Authorities investigating trench collapse that killed worker in Ashburn, Va.
- NTSB publishes preliminary report on fatal gas pipeline explosion in Lexington, Mo.
- Mass. governor slams Trump for ‘dangerous delay’ of $50 million in lead pipe replacement funds
- Ditch Witch West sells first Bulldog trencher to speed up undergrounding work along West Coast
- Centuri awarded nearly $400 million for U.S. gas infrastructure work
- Maryland lawmakers push to curb BGE pipeline spending, citing safety and cost concerns
- Charlottesville, Va., to begin work on 24-inch water line for Rivanna River crossing
- Mass. governor slams Trump for ‘dangerous delay’ of $50 million in lead pipe replacement funds
- City of Albuquerque halts fiber optic construction in response to damage, complaints
- Pasadena, Calif., undergrounding project could take 500 years to finish
Comments