(UI) – According to the Water Environment Federation’s Stormwater Report (WEF Stormwater Report), Virginia’s Arlington County built a stormwater vault system beneath an elementary school to “mitigate the major impacts of flooding.”
The stormwater vaults, constructed underneath Cardinal Elementary School in the county’s Torreyson Run Watershed, are capable of holding over 15 million liters of water, making it “one of the largest precast concrete stormwater vaults in the Mid-Atlantic,” WEF Stormwater Report said.
Flooding from a summer 2019 storm that devastated the area turn what was supposed to be a small vault into a two-part, $18 million stormwater project that took two years to complete. The first phase of construction involved laying underground pipes and junction boxes to redirect water from a previously-installed storm sewer beneath the elementary school to the new vault location. The second phase included the physical vault construction, which ended summer 2023.
A 7-ft. underground pipe carries water to the vaults. After a few hours, gravity brings said water out of the vault and into a designated drainage site. Heavy rainfall in August 2023 put the vault system to the test with success, WEF Stormwater Report acknowledged.
The project is part of the greater "Flood Resilient Arlington" program. According to the government website, Arlington’s stormwater system includes 10,000 storm drains and more than 330 miles of storm sewers.
This story was originally reported by WEF Stormwater Report.
Related News
From Archive

- HDD industry faces challenges as cities push back on fiber drilling disruptions
- 2 workers killed, 1 injured while working on sewer line in Mobile, Ala.
- Tunnel boring continues under Chesapeake Bay for $3.9 billion HRBT Expansion project
- $5.3 billion, 516-mile pipeline to connect Texas to Arizona through New Mexico
- Judge approves construction for key portion of $485 million pipeline in Larimer County, Colo.
- New products: Latest industry developments
- 31 workers rescued after LA tunnel partially collapses
- Ohio Supreme Court rules sewer line location isn’t a ‘defect’ in property dispute
- Faulconer Construction begins rock blasting for water pipeline project in Charlottesville, Va.
- $5.3 billion, 516-mile pipeline to connect Texas to Arizona through New Mexico
Comments