Lane reductions begin on 6th Street in Lawrence, Kan., for sewer work
6/13/2024
(UI) — Traffic was reduced to one lane in each direction on June 12 on 6th Street between Monterey Way and Eldridge Street for storm sewer replacement.
As part of the ongoing 6th Street improvements project, crews discovered a void under the street requiring the replacement of approximately 80 feet of storm sewer.
Traffic will flow head-to-head in this area until the project is completed. The city expects the traffic control measures to remain in place until July 15, 2024, weather permitting.
Related News
From Archive
Sign up to Receive Our Newsletter
- TxDOT advances massive drainage tunnel beneath I-35 in Austin
- Glenfarne Alaska LNG targets late-2026 construction start for 807-mile pipeline project
- U.S. water reuse boom to fuel $47 billion in infrastructure spending through 2035
- $2.3 billion approved to construct 236-mile Texas-to-Gulf gas pipeline
- Major water pipe break in Puerto Rico hits over 165,000 customers
- Pennsylvania American Water launches interactive map to identify, replace lead water service lines
- Trump's tariffs drive $33 million cost increase for Cincinnati sewer project
- Utah city launches historic $70 million tunnel project using box jacking under active rail line
- Tulsa residents warned after sewer lines damaged by boring work
- Fatal trench collapse halts sewer construction in Massachusetts; two workers hospitalized

Comments