Enbridge Fails Pipeline Inspection in Canada
Canada’s National Energy Board (NEB) has issued three Inspection Officer Orders to Enbridge for failure to adhere to worker safety, pipe handling and environmental protection requirements during construction activity on the High Pine Expansion Project near Chetwynd, British Columbia. The NEB orders were issued on August 24, August 27, and September 13, respectively.
NEB Inspection Officers witnessed the following non-compliance matters: failure to construct bridges over watercourses according to specification; failure to protect Riparian Management Areas (environmentally-sensitive areas that occur next to the banks of streams, lakes, and wetlands) from disturbance; and, inadequate sediment and erosion control measures at all watercourse crossings.
In response to the failed inspection, NEB Inspection Officers have ordered Enbridge to complete 27 specific measures to improve worker safety and environmental protection, including:
- Investigate unsafe pipe handling activities
- Assess the adequacy of the High Pine Expansion project oversight
- Immediately cease travel on all bridges and ramps that span two watercourses
- Submit, for NEB review, company action plans to address management of construction activities
Related News
From Archive
- OSHA cites Florida contractors for trench safety violations at sewer and excavation sites
- Biden-Harris administration invests $849 million in aging water infrastructure, drought resilience
- Cadiz to reuse steel from terminated Keystone XL pipeline for California groundwater project
- Texas contractor penalized by OSHA for repeated trench safety violations
- West Virginia approves $67 million for water, sewer projects
Comments