Enbridge Fails Pipeline Inspection in Canada

Canada’s National Energy Board (NEB) has issued three Inspection Officer Orders to Enbridge for failure to adhere to worker safety, pipe handling and environmental protection requirements during construction activity on the High Pine Expansion Project near Chetwynd, British Columbia. The NEB orders were issued on August 24, August 27, and September 13, respectively.
NEB Inspection Officers witnessed the following non-compliance matters: failure to construct bridges over watercourses according to specification; failure to protect Riparian Management Areas (environmentally-sensitive areas that occur next to the banks of streams, lakes, and wetlands) from disturbance; and, inadequate sediment and erosion control measures at all watercourse crossings.
In response to the failed inspection, NEB Inspection Officers have ordered Enbridge to complete 27 specific measures to improve worker safety and environmental protection, including:
- Investigate unsafe pipe handling activities
- Assess the adequacy of the High Pine Expansion project oversight
- Immediately cease travel on all bridges and ramps that span two watercourses
- Submit, for NEB review, company action plans to address management of construction activities
Related News
From Archive

- Intrepid Fiber breaks ground on fiber optic network in Superior, Colo.
- Excavator collides with I-95 overpass in Henrico, Va., causing multi-vehicle crash
- Shrewsbury, Mass., expands sewer inspections and cleaning efforts
- Construction worker killed in trench collapse near Prosperity, S.C.
- Two workers rescued after hours trapped in Mich. trench collapse
- Illinois overhauls Peoples Gas pipeline program, mandates focus on high-risk pipes
- Ameren Illinois to invest $140 million in natural gas pipeline replacement program
- Charlottesville, Va., to begin work on 24-inch water line for Rivanna River crossing
- Mass. governor slams Trump for ‘dangerous delay’ of $50 million in lead pipe replacement funds
Comments