Trial will test contractors' liability for Flint water crisis
ANN ARBOR, Mich. (AP) — Jury selection starts Feb. 15 in a trial to determine if engineering contractors bear responsibility for lead-contaminated water in Flint.
Veolia North America and Lockwood, Andrews & Newman, known as LAN, were not part of the recent $626 million settlement between Flint residents and the state of Michigan, Flint and two other parties.
Attorneys for four Flint children claim Veolia and LAN were negligent in not doing more to get the city to properly treat water that was being pulled from the Flint River in 2014-15. Corrosive water caused lead to leach from service lines serving homes, a disastrous result in the majority Black community.
Veolia and LAN deny liability. Veolia said it had a brief contract with Flint, mostly to address other water issues at the city’s treatment plant. LAN, too, said water quality was not part of its assignment at the plant.
“The problems in Flint were not caused by the alleged failures of outside engineers,” attorneys said last week in a court filing. “They were instead entirely caused by the epic failure of the local and state and federal government at every level.”
Nonetheless, U.S. District Judge Judith Levy declined to dismiss the lawsuit. The trial could last weeks in federal court in Ann Arbor.
Michigan is paying $600 million of the settlement with Flint residents who said they were harmed by lead-contaminated water. After legal fees are subtracted, more than $400 million is expected to go to people and property owners who file claims.
There is no safe level of lead. It can harm a child’s brain development and cause attention and behavior problems.
Related News
From Archive
- Inside Sempra’s 72-mile pipeline with 18 major trenchless crossings
- Trump vetoes bill to finish $1.3 billion Colorado water pipeline
- PHMSA warns of heat risks in aging plastic gas distribution pipelines following deadly Pennsylvania explosion
- Infrastructure failure releases 100,000 gallons of wastewater in Houston; repairs ongoing
- OSHA seeks $1.2 million fine after fatal trench collapse in Connecticut
- Worm-like robot burrows underground to cut power line installation costs
- First tunnel boring machines complete testing for Hudson Tunnel Project
- Infrastructure failure releases 100,000 gallons of wastewater in Houston; repairs ongoing
- Construction jobs stumble into 2026 after weak year
- NWPX grows water infrastructure portfolio with Colorado precast facility

Comments