SAERTEX multiCom reopens North Carolina production facility after 2022 fire
(UI) – SAERTEX multiCom LP's new production facility is up and running again. Originally, operations began in spring 2022 with a brand-new impregnation and dry liner production line. The state-of-the-art facility, with innovative design, is dedicated to increasing inhouse production capacities and capabilities in the United States.
In July 2022, a fire damaged a significant section of the new wet-out equipment. However, the plant is fully operational after seven months of dedicated efforts between SAERTEX multiCom's German and USA-based teams.
A 110,000 ft2 production area with modern sustainable infrastructure is the new home for the glass fiber-reinforced SAERTEX-LINER® manufacturing process of SAERTEX multiCom LP in Huntersville, NC (USA). The flagship and original liner SAERTEX-LINER® MULTI now has an expanded diameter range of up to 64" with an unprecedented and substantial increase in liner lengths, leading up to 40 tons weight delivered to the site.
This modernized facility provides high quality fiber glass reinforced CIPP liners with reduced lead times, supporting installers in achieving their goals in the trenchless rehabilitation of sewers, rain, storm water and supply pipelines.
Larger diameter liners and longer lengths are now produced domestically, “made in America” for the North American market. This extension of the product range is possible due to facility upgrades to the original sewing street, a new technically advanced sewing street, and other improvements surrounding the fiber glass tube manufacturing process.
Additionally, SAERTEX multiCom is now self-impregnating its GRP liners to deliver a ready-to-install UV-CIPP solution to customers in North and Central America - directly to their construction sites when desired.
SAERTEX multiCom will exhibit at the WWETT show in Indianapolis, booth 6207, to introduce to the market the plant's new product range and production capabilities in Huntersville, NC.
Related News
From Archive
- OSHA issues 16 citations following fatal sewer confined space incident
- 27 pipeline safety violations tied to deadly Pa. chocolate factory explosion
- Contractor gas line strike triggers home explosion in Missouri
- LA recovery reports call for $650 million power line burial, major utility upgrades in Pacific Palisades
- Comprehensive microtrenching FAQ: Key insights on the Vermeer MTR516 microtrencher
- T-Mobile to expand fiber broadband infrastructure footprint with $4.9 billion Metronet acquisition
- First tunnel boring machines complete testing for Hudson Tunnel Project
- NWPX grows water infrastructure portfolio with Colorado precast facility
- Cityside launches $100 million fiber build in Corona, Calif.
- FiberLight to build 1,400-mile West Texas dark fiber network in $350 million expansion

Comments