USACE starts Lahaina sewer project a year after deadly wildfire
MAUI, Hawaii (UI) — The U.S. Army Corps of Engineers plans to commence construction on a critical sewer line project for the Kilohana temporary housing development, which will support 169 housing units for wildfire survivors. This project will enhance the community sewer system for Fleming Road residents and allow for future expansion.
The Lahaina Emergency Sewer System project will commence on August 12. It involves installing 1,000 linear feet of 12-inch sewer main along Malo Street and 1,500 linear feet of 8-inch sewer main along Fleming Rd. Additionally, 26 lateral 6-inch sewer lines will be prepared for future hookup. Federal, state and local officials will be present for the ground blessing ceremony scheduled for Friday, August 9 at the Wahikuli park.
During construction, expect intersection closures and alternate access routes to ensure safety and efficiency.
Planned Construction Traffic Routes and Dates:
- Aug. 12 – Sept. 13: The Fleming Rd/Honoapiilani Hwy intersection will be closed. Access from Ainakea Rd/Fleming Rd to Honoapiilani Hwy will be restricted to construction vehicles and residents of Fleming Rd. Residents will have driveway access except when work is being done on their individual driveway. Access from Fleming Rd/Malo St to the lift station will be limited to construction vehicles and County of Maui personnel.
- Sept. 13 – Nov. 8: Access from Fleming Rd/Lower Cane Rd to Fleming Rd/Ainakea Rd will be restricted to construction vehicles and residents. Residents will have driveway access except when work is being done on their individual driveway. Access from Fleming Rd/Malo St to the lift station will be limited to construction vehicles and County of Maui personnel.
USACE has been instrumental in designing and preparing the Kilohana Temporary Housing Site, conducting earthwork and utilities installation. This infrastructure enables FEMA to install modular units, providing much-needed temporary housing for wildfire survivors as they rebuild their lives.
The installation of a permanent sewer line is a significant milestone in the recovery process and a lasting improvement to community infrastructure. It will benefit Lahaina and the Wahikuli neighborhood by allowing residents to transition from cesspools to a public sewer system, which is more sanitary, environmentally conscious, and requires less maintenance.
USACE remains committed to supporting the community and ensuring that all construction activities are conducted safely and efficiently. We appreciate the patience and understanding of residents as we work to provide essential temporary housing for wildfire survivors.
Related News
From Archive

- HDD industry faces challenges as cities push back on fiber drilling disruptions
- 2 workers killed, 1 injured while working on sewer line in Mobile, Ala.
- Tunnel boring continues under Chesapeake Bay for $3.9 billion HRBT Expansion project
- $5.3 billion, 516-mile pipeline to connect Texas to Arizona through New Mexico
- Judge approves construction for key portion of $485 million pipeline in Larimer County, Colo.
- New products: Latest industry developments
- 31 workers rescued after LA tunnel partially collapses
- Ohio Supreme Court rules sewer line location isn’t a ‘defect’ in property dispute
- Faulconer Construction begins rock blasting for water pipeline project in Charlottesville, Va.
- $5.3 billion, 516-mile pipeline to connect Texas to Arizona through New Mexico
Comments