A Minnesota court offers mixed views on water permit for mine
ST. PAUL, Minn. (AP) — A Minnesota appeals court issued a mixed opinion in a complicated case contesting one of the key permits that a St. Paul-based company needs to build what would be the state’s first copper-nickel mine.
The Minnesota Court of Appeals reversed a decision by regulators to issue the PolyMet Mining Corp. a water quality permit for the project. It now goes back to the Minnesota Pollution Control Agency to determine whether any pollution discharges from the mine into groundwater would violate the federal Clean Water Act.
However, the three-judge panel rejected several other arguments from PolyMet’s opponents. Among them, there was a demand for more stringent limits on the treated wastewater that’s discharged from the mine and a call for a contested case hearing to gather more evidence and testimony on certain aspects of the permit before a neutral judge, Minnesota Public Radio News reported.
Both sides said they were happy with the decision. “This is a huge victory,” said Paula Maccabee, advocacy director and counsel for WaterLegacy, one of the groups that challenged the permit. Jon Cherry, PolyMet president, chairman and CEO, said the company is “pleased that we have prevailed on the majority of the issues” and court has narrowed the case down to a single dispute.
While it means an additional delay for the contentious project, it does not put a stop to the $1 billion open-pit mine that PolyMet has proposed near the towns of Babbitt and Hoyt Lakes.
“We conclude that the PCA erred by not properly considering whether the federal Clean Water Act applies to any future discharges from PolyMet’s facility to groundwater. But we conclude that there is no reversible error with respect to all other issues that have been raised by the parties,” the judges wrote in the 39-page opinion.
The ruling is just the latest step in a long legal battle that opponents to the PolyMet project have waged since the state first approved it more than three years ago. Several other key permits that PolyMet needs to begin construction also remain tied up in litigation or have been remanded to state agencies for additional work.
The company says the mine would create hundreds of jobs while supplying metals that the U.S. economy needs. Environmentalists have fought it because of the potential for acid mine drainage.
Related News
From Archive
- Inside Sempra’s 72-mile pipeline with 18 major trenchless crossings
- Trump vetoes bill to finish $1.3 billion Colorado water pipeline
- PHMSA warns of heat risks in aging plastic gas distribution pipelines following deadly Pennsylvania explosion
- Infrastructure failure releases 100,000 gallons of wastewater in Houston; repairs ongoing
- OSHA seeks $1.2 million fine after fatal trench collapse in Connecticut
- Worm-like robot burrows underground to cut power line installation costs
- First tunnel boring machines complete testing for Hudson Tunnel Project
- Infrastructure failure releases 100,000 gallons of wastewater in Houston; repairs ongoing
- Construction jobs stumble into 2026 after weak year
- NWPX grows water infrastructure portfolio with Colorado precast facility

Comments